Backfill Plants

Portfolio of Projects - Backfill Plants


Cemented Rockfill Plant

Newmont Mining Corporation
Deep Post Mine
Carlin, Nevada, USA

This multi-level plant is designed for automated backfill production at Newmont's Deep Post Mine. The backfill plant utilizes a twin shaft mixer at the 4084 level, to mix backfill, discharging directly into haul trucks.

Aggregate is delivered underground by truck to a 1300 ton aggregate storage silo before feeding the mixer. Cement and flyash are pneumatically conveyed from surface and stored in bins on the 4290 level. Here, a blend is produced for delivery to the backfill area or an underground shotcrete plant. Once in the backfill area, blended cement is conveyed directly to the mixer or alternately, to the colloidal mixer for slurry batching.

All process are controlled by the operator using PC control, as the operator interface. Fibre optics are used to communicate with the five PLCs in the system.

Redundant features in the backfill plant ensure reliability. In the event the slurry mixer is unavailable, water and cement may be metered directly to the mixer. Should the main backfill mixer be unavailable, trucks may receive aggregate and slurry at the upper truck bay, ensuring backfill production continues.

SIZE / CAPACITY

  • 150 cubic yards per hour

SERVICES PROVIDED

  • Conceptual Design
  • Struct./Mech. Engineering
  • Design & Supply of Control System
  • Supply/Fabrication of All Equipment
  • Supervision of Equipment Installation
  • Commissioning and Training

SUPPLIED EQUIPMENT

  • Twin Shaft Mixer
  • Colloidal Mixer
  • Two Cement/Flyash Bins
  • Pneumatic Conveying System
  • Eight Screw Conveyors
  • Ribbon Blender
  • 1300 ton Aggregate Storage Hopper
  • Apron Feeder
  • Two Belt Conveyors
  • Backfill Mixer Structure
  • Control Room with MCC/PLC System
  • Dust Collection System
  • Pneumatic Control System

Back to Top

Cemented Rockfill Plant

Minera Meridian LTDA
El Penon, Chile

The Material Handling Team designed, manufactured, and commissioned this automated backfill plant. It is located in the driest location on earth, the Atacama dessert in northern Chile.

This plant combines cementitious slurry with coluvium (aggregate), known as 'chusca'. A Thiessen Tornado slurry system is utilized to prepare slurry in multiple batches and store it in a holding tank. Aggregate is stockpiled above a tunnel conveyor and is then conveyed to a pugmill via a conveyor scale.

The process is a hybrid system, using automated slurry batching combined with a continuous process at the pugmill where the aggregate and slurry are mixed before discharging to the backfill holding hopper and haul-truck. The system is mostly self-cleaning, using the Tornado's colloidal mixer and slurry pump to purge all lines, the pugmill and gob hopper.

This project was particularly challenging due to the complexity of coordinating the continuous processes to sized truckloads up to 20 tonnes. Two variable frequency drives (VFDs), a conveyor scale, and a variable speed/reversing peristaltic pump were utilized within the system to ensure consistent, high quality backfill.

The unique feature of this plant is the self cleaning purge cycle inherent within every batch. The system self-cleans in this manner and may continue this way for shifts of any duration. At the end of a shift, a wash formula, (water only), be run for a final cleaning.

SIZE / CAPACITY

  • 70 tons per hour

SERVICES PROVIDED

  • Conceptual Design
  • Struct./Mech. Engineering
  • Design & Supply Of Control System
  • Supply/Fabrication of all Equipment
  • Supervision of Equipment Installation
  • Commissioning and Training

SUPPLIED EQUIPMENT

  • Two Aggregate Conveyors
  • Pugmill Backfill Mixer
  • Backfill Holding Hopper
  • Backfill Mixer Support Structure
  • 125 Ton Cement Silo
  • Screw Conveyor
  • 1350 Litre Colloidal Mixer
  • Slurry Surge Tank
  • Paristaltic Slurry Pump
  • Dust Collection System
  • Control Room/PLC/MCC System
  • Pneumatic Control System

Back to Top

Cemented Rockfill Plant

Getchell Gold Corporation
Turquoise Ridge Mine
Golconda, Nevada, USA

The Material Handling Team was the successful bidder in the design, manufacture and commissioning of Getchell Gold's Turquoise Ridge backfill system. The plant is comprised of silos, feeders, weigh-bins, diverters and mixers at various locations throughout the mine.

Cement and flyash from surface silos and aggregate from the surface batch plant are fed through borehole feed lines to a series of transfer and weighing stations underground. The material is then mixed in a 10 cubic yard Besser mixer where it is fed into haul trucks to be used in their underhand cut and fill operations.

The plant also includes a Thiessen Tornado 1000 on the surface which feeds cement slurry to the various underground levels where it is sprayed over development waste for the production of further cemented rockfill.

SIZE / CAPACITY

  • 150 tons per hour

SERVICES PROVIDED

  • Struct./Mech. Engineering
  • Design & Supply Of Control System
  • Supply/Fabrication of all Equipment
  • Supervision of Equipment Installation
  • Commissioning and Training

SUPPLIED EQUIPMENT

  • 80 Ton Aggregate Storage Hopper
  • Two Aggregate Weigh Hoppers
  • Aggregate Transfer Chute
  • Four Belt Conveyors
  • Slump Mixer
  • Two 125 Ton Cement & Flyash Silos
  • Two Cement & Flyash Weigh Hoppers
  • Water Weigh Hopper
  • Seven Screw Conveyors
  • Cement Storage Hopper
  • 1000 Litre Colloidal Mixer
  • Slurry Dispensing Head
  • Control Room/MCC/PLC System
  • Pneumatic Control System
  • Support Structures For All Equipment
  • Fully Cladded and Insulated Enclosures

Back to Top

Concrete Batch Plant

Kahama Mining Corporation
Bulyanhulu Gold Mine
Tanzania, Africa

The Material Handling Team was commissioned by Kilborn SNC Lavalin to supply a complete concrete batching plant to be used for surface and underground construction at Sutton Resources' remotely located Bulyanhulu minesite in Tanzania, Africa.

In order to meet shipping deadlines, The Material Handling Team completed all design and fabrication, including all control PLC and MCC systems, in six weeks. A subsequent flyash upgrade was also supplied, which features their innovative bulk bag unloading system, and commissioning of the entire plant.

SIZE / CAPACITY

  • 80 cubic meters per hour

SERVICES PROVIDED

  • Conceptual Design
  • Struct./Mech. Engineering
  • Design & Supply Of Control System
  • Supply/Fabrication of all Equipment
  • Supervision of Equipment Installation
  • Commissioning and Training

SUPPLIED EQUIPMENT

  • Aggregate Infeed Hopper
  • Aggregate Weigh Hopper
  • Aggregate Conveyor
  • Two 40 Ton Cementitious Silos
  • Drive Through Silo Supports
  • Screw Conveyor
  • Cement & Water Weigh Hoppers
  • Bulkbag and 50 kg bag Unloaders
  • Pneumatic Charge System
  • Dust Collection System
  • Control Room/MCC/PLC System
  • Pneumatic Control System

Back to Top

Cemented Rockfill Plant

Cominco Limited
Polaris Mine
Little Cornwallis Island, Nunavit, Canada

Located only 100 km from the magnetic north pole, the Cominco Polaris lead-zinc mine is the most northerly operating mine in the world. When working north of the seventy-fifth parallel, the Arctic Ocean only allows a six week window in mid summer to allow sea access by freighter. Polar bears, caribou, arctic fox and musk ox are seen almost daily, within the boundaries of the mine.

In this project undertaken by The Material Handling Team, 27 truckloads of equipment had to be dockside in Montreal within a few months or the project would be delayed for a year. The Material Handling Team delivered all equipment as required.

The plan called for 8" minus aggregate, permanently frozen by Arctic conditions, to be brought in by haul truck, conveyed and stored in a 375 ton bin. The rock was then fed by a series of apron feeders, vibratory feeders, and conveyors through a pre-heat stage and hot water rotary bath to a second 75 ton storage bin.

Here, a Thiessen Tornado, employing four Colcrete-Eurodrill colloidal mills combined a cementitious slurry with the heated rock. 30 ton haul trucks were then loaded with cemented rockfill for use in the underground mine. The heated CRF had to withstand unbelievable ambient temperatures approaching -70 degrees C, with wind chill.

A single Modicon PLC system with dual touchscreens was used to monitor and control the entire plant. The Material Handling Team also provided site supervision and startup assistance to Cominco in prime Arctic conditions, October to April.

SIZE / CAPACITY

  • 8190 tons per hour (Screening Plant)
  • 125 tons per hour (Mixing Plant)

SERVICES PROVIDED

  • Conceptual Design
  • Struct./Mech. Engineering
  • Design & Supply Of Control System
  • Supply/Fabrication of all Equipment
  • Supervision of Equipment Installation
  • Commissioning and Training

SUPPLIED EQUIPMENT

  • 2000 Litre Colloidal Mixer
  • Cement & Water Weigh Hoppers
  • Calcium Chloride Weigh Hopper
  • Four Screw Conveyors
  • Three Cementitious Silos
  • Dust Collection System
  • Progressive Cavity Pump
  • Cement Slurry Spraybars
  • Truck Dump Hopper
  • Cement Bag Unloading System
  • Two Apron Feeders
  • Two Belt Conveyors
  • 375 Tonne Aggregate Storage Bin
  • Rotary Hot Water Bath System
  • 75 Tonne Surge Bin
  • Vibratory Feeder and Screen Deck
  • Control Room/MCC/PLC System
  • Pneumatic Control System
  • Two 10,000 Gallon Water Tanks
  • Heat Exchanger

Back to Top

Cemented Rockfill Plant

Homestake Canada Inc.
Eskay Creek Mine
Eskay Creek, BC, Canada

Eskay Creek Mine is located in British Columbia, north of Stewart and is one of Canada's premier gold mine operations.

The Material Handling Team was commissioned by Homestake Canada Inc. to design and manufacture a cemented rockfill plant. This batch plant, located at the mine's lower portal, mixes aggregate, cement, and water, yielding a premixed cemented rockfill. The plant incorporates a 3000 litre Teka pan mixer. The entire process runs automatically using a Modicon programmable controller and touchscreen, which is connected via a communications network to other PLCs at the mine.

This plant was prefabricated and shipped in modules. The Material Handling Team's contract included civil engineering, motor control center, erection supervision and operator training. This plant is equally capable of producing high quality concrete and shotcrete, in addition to cemented rockfill.

SIZE / CAPACITY

  • 50 tons per hour

SERVICES PROVIDED

  • Conceptual Design
  • Struct./Mech. Engineering
  • Design & Supply Of Control System
  • Supply/Fabrication of all Equipment
  • Supervision of Equipment Installation
  • Commissioning and Training

SUPPLIED EQUIPMENT

  • 2 Compartment Aggregate Storage Bin
  • Aggregate Weigh Hopper
  • Aggregate Belt Conveyor
  • Teak Pan Mixer
  • Cement Silo
  • Cement Weigh Hopper
  • Concrete Holding Hopper
  • Dust Collection System
  • Water Storage Tank
  • Control Room with MCC/PLC System
  • Mixer and Silo Support Structure
  • Fully Cladded and Insulated Enclosures
  • Pneumatic Control System

Back to Top

Concrete Batch Plant

Sistema Hidraulico
Portal de Entrada
Yacambu, Estada Lara, Venezuela

The Material Handling Team was contracted to design, supply, and commission a pre-mix concrete batch plant at the portal of this irrigation tunnel. This batch plant produces shotcrete and concrete for tunnel lining. This plant featured a 4 yd³ Voeller pan mixer and is PLC controlled. The plant was commissioned by Material Handling Team personnel who also performed operator training on-site.

This project involves a 24 km tunnel in Los Andes spurs, in western Venezuela. The tunnel is to supply irrigation water from the Yacambu valley to the neighboring Quibor valley. The contrast between the lush jungle environment at Portal de Entrada and the dry desert climate at the other end, Portal Salida is remarkable.

SIZE / CAPACITY

  • 60 cubic meters per hour

SERVICES PROVIDED

  • Conceptual Design
  • Struct./Mech. Engineering
  • Design & Supply Of Control System
  • Supply/Fabrication of all Equipment
  • Supervision of Equipment Installation
  • Commissioning and Training

SUPPLIED EQUIPMENT

  • Aggregate Loadout Hopper
  • Three Belt Conveyors
  • Aggregate 3 Position Flop Chute
  • Aggregate Storage Bins
  • Three Cement Silos
  • Three Screw Conveyors
  • Cement Weigh Hopper
  • Water Weigh Hopper
  • Pan Mixer
  • Concrete Holding Hopper
  • Dust Collection System
  • Pallet Lift System
  • Equipment Support Structure
  • Control Room/MCC/PLC System
  • Pneumatic Control System

Back to Top

Concrete Batch Plant

Sistema Hidraulico
Portal Salida
Quibor, Estada Lara, Venezuela

This project, as described previously in the Yacambu project, involves the same 24 km irrigation tunnel, in Los Andes spurs. As with the plant at Portal de Entrada, in the Yacambu valley, The Material Handling Team was contracted to design, supply, and commission a concrete batch plant at the Portal Salida featuring a Voeller pan mixer. This plant is also PLC controlled and included an Motor Control Center as part of the automated package.

The project itself involves tunneling from the outlet of the tunnel in the Quibor valley, towards Yacambu. The tunnel, when completed, will be turned over to the Environmental and Natural Resources Ministry of Venezuela.

SIZE / CAPACITY

  • 60 cubic meters per hour

SERVICES PROVIDED

  • Conceptual Design
  • Struct./Mech. Engineering
  • Design & Supply Of Control System
  • Supply/Fabrication of all Equipment
  • Supervision of Equipment Installation
  • Commissioning and Training

SUPPLIED EQUIPMENT

  • Aggregate Loadout Hopper
  • Three Belt Conveyors
  • Aggregate 3 Position Flop Chute
  • Aggregate Storage Bins
  • Three Cement Silos
  • Three Screw Conveyors
  • Cement Weigh Hopper
  • Water Weigh Hopper
  • Pan Mixer
  • Concrete Holding Hopper
  • Dust Collection System
  • Pallet Lift System
  • Equipment Support Structure
  • Control Room/MCC/PLC System
  • Pneumatic Control System

Back to Top